More electrical bids are lost on paperwork than on price. A GC's insurance exhibit usually asks for four things beyond the basic certificate of insurance, and each one has to be set up on the policy before anyone asks:

  • Additional insured endorsement
    The GC (and often the owner) gets defense and coverage under your liability policy for claims arising from your work. It must be an endorsement, not just a note typed on the certificate.
  • Waiver of subrogation
    Your carrier gives up its right to recover from the GC after paying a claim. Needed on both liability and workers' comp for most commercial exhibits.
  • Primary and noncontributory wording
    Your policy pays first and does not seek contribution from the GC's policy. Again, an endorsement, arranged in advance.
  • Per-project aggregate
    Your $2M general aggregate applies separately to each project, so one bad job does not erode the limits another GC is relying on.

Send us the GC's insurance exhibit before you sign the subcontract. We check it against your policy line by line, flag anything you do not carry (a $5M umbrella on a $40,000 tenant fit-out, for example), and issue certificates same business day once the endorsements are in place.

Read the full guide: what general contractors require, decoded
Organized interior of an electrician's service van with shelving, wire spools, and tools
Everything in this van rides on a policy: the vehicle on commercial auto, the wire, tools, and test gear on inland marine. A photo inventory like this is what a theft claim gets paid from.

Guide · GC Requirements

What general contractors require, decoded

Every electrical subcontract comes with an insurance exhibit, and most of it is boilerplate that nobody explained to you. Here is each common requirement in plain language, what it actually does on your policy, what to check before you sign, and what to send back when a requirement cannot be met as written. From Segreve & Hall Insurance, Andover, MA.

The exhibit saysWhat it meansWhat to check
Additional insuredThe GC, and often the owner, is added by endorsement to your liability policy, so your policy defends and covers them for claims arising out of your work.The endorsement must exist on the policy. Typing the GC's name on a certificate adds nobody. Ask which form the exhibit wants, ongoing operations (CG 20 10), completed operations (CG 20 37), or both; GCs increasingly require both, and for electricians the completed operations piece is the one that responds when finished work causes damage later.
Waiver of subrogationAfter paying a claim, your carrier normally could pursue whoever was at fault. The waiver gives up that right against the GC. Exhibits usually require it on both liability and workers' comp.It is an endorsement on each policy named, sometimes with a small charge. It must be in place before the loss, not negotiated after one.
Primary and noncontributoryYour policy pays first for claims from your work, and does not ask the GC's policy to share the loss.Again, endorsement language on your liability policy. Standard for commercial work, but confirm your carrier's form satisfies the exhibit wording.
Per-project aggregateYour general aggregate limit applies separately to each project instead of being shared across all your work that year.Worth having if you serve several GCs at once. Without it, one bad loss on another job can erode the limits this GC is counting on.
Notice of cancellation to the certificate holderThe GC wants warning if your policy cancels or nonrenews mid-project.What the holder actually receives is governed by your policy terms and any specific endorsement. Do not promise notice periods your policy does not provide; offer what the policy supports.
Umbrella or excess limitsTotal liability limits above your primary $1M, commonly $2M to $5M total on larger, condo, municipal, or institutional work.Price it before you bid. An umbrella is normally the cheapest added limit you can buy, but it cannot be bound retroactively, and discovering the requirement after award compresses both the timeline and your margin.
Workers' comp with no gamesOfficers properly included or formally opted out, and no uninsured subs underneath you.Their payroll and their injuries become yours at audit and at claim time. Collect certificates from your own subs before they start, the same way the GC collects yours.

Certificate turnaround, honestly

Standard certificates go out the same business day once your policy and the needed endorsements are in place. The delays GCs complain about are almost never typing speed. They are exhibits that arrive the morning a check is being held, requiring endorsements nobody ordered, limits nobody carries, or a holder name and job description that do not match the subcontract.

The fix is boring and it works: send your agent the insurance exhibit when you receive the subcontract, before you sign it, and let the endorsements be set up at binding or renewal. Then every certificate for that GC is a five minute task all year.

When a requirement cannot be met as written

It happens: a $5M umbrella on a small fit-out, a cancellation notice period your policy does not offer, an endorsement form your carrier does not file. Do not sign and hope, and do not silently send a certificate that implies compliance you do not have. Send back a short, specific exception note instead:

  • Name the exact clause you cannot meet, by section, not a general objection.
  • State what you do carry and offer the closest available alternative, for example the umbrella limit you can bind and its price effect on the bid.
  • Ask whether the requirement flows from the owner's own insurance program. Owner controlled programs set some of these numbers, and GCs can often get a variance confirmed in writing.
  • Get the resolution in writing before mobilizing, even if it is one sentence in an email.

A plain version reads: "Our policy provides 30 days notice of cancellation to the named insured, and we cannot endorse a longer notice to certificate holders. We carry $1M per occurrence and $2M aggregate liability with additional insured, waiver of subrogation, and primary wording as required. Please confirm this is acceptable, or let us know if the owner requires the higher umbrella limit, which we can bind at an added cost to the contract." Specific, honest, and easy for a project manager to approve.

The GC's exhibit asks for limits higher than the job seems to warrant. Can I push back?

You can ask, and the exception note approach above is the way to do it. Understand the mechanics first: exhibit limits usually flow down from the owner's requirements or the GC's own insurance program, so the project manager may have no authority to waive them. If the higher limit stands, price the added premium into the bid rather than absorbing it, and keep the umbrella after the job, since the next exhibit will likely ask for it too.

Can I just note the extra requirements on the certificate?

No. A certificate is evidence of coverage in force; the words typed on it do not amend the policy, add insureds, or waive subrogation. If a claim arrives and the endorsement was never issued, the certificate language will not rescue the gap. This is the single most common misunderstanding in subcontract paperwork, and it is why GCs with good risk managers request the endorsement pages themselves.